Booklet 1 – Standards (Draft)
สำนักงานพัฒนารัฐบาลดิจิทัล
เนื้อหา
หน้า 1
Booklet 1 – Standards (Draft)
หน้า 2
2 Preface The emergence of the Internet as a universal network and the continued advancements and maturity of Web technology have served as catalysts for a well - designed data centers. Government agencies across the region have data centers that are burdened by aging IT environm ents that consume an increasing amount of the a nnual operating budget and ma y, in turn, lead to technological obsolescence. In many cases, th ese organizations recognize the need for a truly transformative modernization of IT systems and processes . Thailand government agencies data centers are also in the same situation with most of the agencies data centers scattered all around the country. Electronic government agency (EGA) of Thailand has been given the responsibility of leading the digitization initiatives in Thailand. EGA soon realized that there is an urgent need for the modernization of all the agency data centers. As part of the modernization initiative, EGA also realized that data centers across the agencies need to adopt industry specific standards. Adoption of standards is quite essential in the whole modernization initiative, as it provides agencies a lev el of assurance that the service they are providing meets a proscribed level of measurement for performance, safe operations, etc . Apar t from that, standards also provide cost savings in terms of energy and cooling, better security features, augmented services levels, better design and location and better service level agreements. B y providing a common method of comparison, agencies can c hoose the level of standards they adopt based on their individual priorities. As part of data center modernization strategy, Frost & Sullivan in conjunction with EGA conducted a focus group discussion to understand the current adoption levels of data cent er standards among government agencies. With the knowledge of current adoption levels of agency data centers, Frost & Sullivan was able to develop future adoption level of for all the government agencies of Thailand. Globally different government bodies h ave adopted data center standards in their respective regions. Uptime and TIA 942, most popular data center standards are being recommended by the Japanese and Malaysian government. Australia, Malaysia and USA have defined the PUE specific standards for it s government agencies. Likewise various governments have defined the standards for different function areas of the data center. The standards booklet contains information about the importance and need of standards, examples of adoption of standards, fiv e core elements of standards, relevance and challenges among standards, maturity model for nineteen sub parameters of standards, benefit realization of standards, adoption scenarios of standards and finally service level agreements (SLA) for colocation and cloud computing.
หน้า 3
3 Contents 1. Executive Summary ................................ ................................ ............................. 4 2. Need for the Standards ................................ ................................ ........................ 5 3. Importance/Relevance of data center standards ................................ ................. 8 4. Data Center Standards current situation in Thailand ................................ ........... 9 5. Data Center Standards by Functional Areas ................................ ..................... 1 2 6. Refined Maturity Model for Data centers ................................ ........................... 18 7. Benefit Realization – Standards ................................ ................................ .......... 22 8. Current State of Agency data center in Thailand ................................ .............. 25 9. Frost & Sullivan Analysis of Future State for Standards for Data Centers ......... 27 10. Service Level Agreements - Colocation ................................ ........................... 28 11. Service Level Agreements - Third party Cloud ................................ ................ 35
หน้า 4
4 1. Executive Summary Governments across the world utilises various standards for reliable, cost effective and higher utilization of their data infrastructure assets. The standards enable various important purposes for the government viz. securing sensitive IT assets, securing record and data of public sector agen cies, energy efficiency, consumption based and higher competency infrastructure. Data center industry is more than 20 years old and there are sizable international bodies that have been developing standards for it. The standards have been developed for dif ferent components of the data center and also for a particular outcome. The whole data center industry is quite complex to run and these standard guidelines help the industry to run the data centers smoothly and efficiently. But these standards are not eas y to follow and they are quite challenging. The technology savings approach cover everything from facility lighting to cooling system design, and have proven useful in helping some companies curb the trend of rising data center energy consumption. Most organizations still lack a cohesive, holistic a pproach for reducing data center energy use. Today’s data centers are subject to more rigorous compliance standards than ever before. Expectations from customers regarding uptime, environmental impact, quality, operations, security and safety are encourag ing best practices from colocation providers and operators. Various government acencies across the globe are on a constant series of change with respect to their Data Center Strategy. Many of them are either revamping and modernising their data centers or are into a consolidation phase or are simply into the growth phase of the data center journey of the agencies. These strategies are bolstered by the standards that they will use for the overall strategy to come into effect and for future investments. Ther e are many examples of international standards available including Uptime and TIA 942. Both standards provide tiers for service availability for data centers. The standards for energy and power are energy star, NABERS and ASHARE. The standards related to s ervices is t he PT DCI standard and HIPPA. LEED and BISCI are design standards for data centers. These standards are being adopted my government globally. Standards adoption is at nascent stage in Thailand data center market and adoption is quite low compa red to other south Asian economies It is challenging for the data centers to have knowledge about which standards to adopt and which not to adopt. As a part of GDCM Strategy, a standards framework has been designed for the government agencies in Thailand with five core areas (energy and power, design and structure, server storage and utilization, location and site and SLA’s).The five core areas have been further divided into nineteen core sub - parameters and each of nineteen sub - parameters have five levels of adoption. The future adoption levels developed are the minimum level that each of the agencies should adopt and if required they can further go up in the chain. We also highlighted the adoption scenarios for the each of the nineteen sub parameters for four types of future agency data centers. In some cases the government agencies would be using the services of third party colocation provider and cloud computing players. Frost & Sullivan have developed detailed components of service level agreements for both colocation and cloud computing, as this would help Thailand government agencies developing their own SLA’s.
หน้า 5
5 2. Need for the Standards Rapidly - increasing traffic is driving the data storage for governmanet agencies as well as enterprises , which is resulting in continuous expansion of the data center. The number of web and mobile applications being developed and used is on the rise thereby driving demand for web space. The advent of newer technologies such as data analytics, big data, Inter net - of - Things, etc. is increasing the amount of data that is collected and stored. Fuelled by these factors among others, the global data centers industry is expected to grow across the world. Data centers are essential to the functioning of modern economy and are found nearly in every sector of the economy: government institutions ,financial services, high - tech universities, media, telecommunication, , and retail. The overall data center workloads are expected to double from 2013 to and the approxima tely five exabytes of data online in 2002 rose to 750 EB in 2009; by 2021 it is expected to cross the 35 zettabytes level. The growth of data centers is also driven by the evolution of cloud - based services and smart cities. By 2018, more than 78% of worklo ads will be processed by cloud data centers and almost 22% will be processed by traditional data centers, Some of the world’s biggest technology organizations (e.g., Microsoft, Google, IBM, and Cisco) have taken on the development of smart cities for which the data centers will provide the infrastructure support. For example, data centers will be storing and processing the data received through sensors to detect excessive air pollution, integrated traffic controls, and education systems. Overall, the number of data centers is expected to increase dramatically in the near future. Considering the growth expected in data center industry, interest is growing to reduce the energy consumption and make data centers more energy efficient. Since data centers operate 24/7 and are highly energy intensive, the energy intensity of a data center may be 10 to 100 times of a typical commercial building. Rising energy prices are also increasing the operating cost of data centers and it has been reported that global data center carbon emissions will grow 7% year - on - year through 2020. It is estimated that achieving just half o f the technologically feasible savings through adopting best practices could cut electric use by 40% in data centers. The technology savings approach cover everything from facility lighting to cooling system design, and have proven useful in helping some c ompanies curb the trend of rising data center energy consumption. Most organizations still lack a cohesive, holistic approach for reducing data center energy use. It is not considered sufficient to simply recognize the need to save energy and improve effi ciency; one need to quantify key benefits associated with energy efficient practices and prioritizes actions to achieve them. To assist organizations measure the savings from adopting best practices, associations such as The Green Grid have developed metri cs such as Power Usage Effectiveness (PUE) and Data Center Infrastructure Efficiency. Historically, mainframes had their own unique requirements, given the separate physical space and room utilities with limited movement post installation However, today d ata center environment is no longer static and characterized by the need for greater integration, outsourcing to third party environments and need for changes in environment to accommodate new technologies.
หน้า 6
6 To enable effective management and provisioning of services in the dynamic environment, standards play a role in recommending practices and performance requirements and thereby provide a framework for best practices Today’s data centers are subject to more rigorous compliance standards than ever before. Expectations from customers regarding uptime, environmental impact, quality, operations, security and safety are encouraging best practices from colocation providers and operators. Certif ications such as ISO, Uptime, Leed and SSAE16 are just some of the standards proving of significant importance to those in the market for colocation data centers. To help differentiate data centers, service providers and data center operators publish cert ifications for the following regulatory and standards organisations: Various government acencies across the globe are on a constant series of change with respect to their Data Center Strategy. Many of them are either revamping and modernising their data c enters or are into a consolidation phase or are simply into the growth phase of the data center journey of the agencies. These strategies are bolstered by the standards that they will use for the overall strategy to come into effect and for future investme nts. Effectively as a result the standards have evolved over time and will continue to be in that mode based on: Experience of other players and agencies Geographical nuances, technology needs, behaviour of agencies, data types, weather conditions Tech nology used, robustness required Budgets Global best practices Over the past 20 years as and when the data centers started gaining prominence, data centers were historically designed in the absence of established standards or best practices. This had many network administrators faced with the challenge of choosing technologies and deciphering how to properly implement them into an often - undersized space that is responsible for securely and reliably providing all the existing and future services to an enterprise. Not just the technological components but areas like security, design and construction were ad - hoc as similar to developing a commercial real - estate. Over time, various standards started coming to shape - some developed by international bodies on specific areas of data center whilst some standard practices started gaining prominence as an outcome of lessons learnt across various implementations.
หน้า 7
7 Fig 1 : Various International Standards in the market These standards have been developed with years of research and experience across fixed set of areas. For example, TIA has TIA - 942 Telecommunications Infrastructure Standards for Data Centers, the first standard to specifically address data center infrastr ucture. Intended for use by data center designers early in the building development process, and covers the following: > Site space and layout; > Cabling infrastructure > Tiered reliability > Environmental considerations. These standards use international best practices and offer great results, compliance and certifications in many cases which are often treated as gold standards by various agencies and companies. However, various companies and agencies do not prescribe to such standards alone as usually meeting the stringent guidelines come at a significant cost which to many organisations do not seem to be worthwhile proposition. A lot of technology or service provider companies also develop compliance to these standards hence as a result, if agencies follow a particular standard, it may mean that they would get restricted to utilising the services of select few companies thus not able to make specific choices. Which is why, various agencies practice their own standards and publ ish their own standard guidelines to the providers to enable an ecosystem of growth, revolution as well as best cost. However, many government agencies follow best practices approach and the standard fulfilment for few select areas while publish their own guidelines at their discretion on what works right for them. Nabers US EPA Uptime Institute ISO Energystar SSAE 16 Leed Open IX ASHRAE HIPAA ANSI/TIA PCI DC Star Audit ISAE BCA/IDA BISCI
หน้า 8
8 3. Importance/Relevance of data center standards Data centers has been in the market for more than 20 years now and the overall dynamics of data center industry has changed a lot since then. In the last decade, data center has be come huge, complex and challenging to operate. The cost of data center downtime has increased significantly for companies in the last couple of years. The study of US data centers quantifi es the average cost of an unplanned data center outage at slightly more than US$7,900 per minute and this is a 41% increase from the $5,600 it was in 2010. Data center cannot afford downtime or inefficiency, as it leads to increased cost and unhappy custom ers. Data center operators in the last couple of year have improved the availability and efficiency of data centers by adopting globally recognized data center standards. Efficient data centers Data center standards play an important role when it comes down to help ch oose which data center service to use. Data center customers rely on standards as a method of performing comparative analysis on competing suppliers. By providing a common method of comparison, standards help insulate customers from the need to make their decisions on solely on the basis of the claims of a provider. A prime example is found with the Tier system originally developed by the Uptime Institute. Comprised of four escalating Tiers that prescribed the physical componentry required to deliver specif ic levels of reliability the system became recognized as the de facto standard for reliable data center design. Compar ative analysis As the data centers are becoming complex, rising energy costs are increasing the operating costs of running a data center. Data Centres consume an immense amount of power to perform functions reliably and effectively. The electrical costs in data centres t ypically accounts for 40 - 60% of the total operating costs. Improving energy efficiency of a data centre is extremely beneficial as it reduces the costs of operation of data center. Data center operators can use below mentioned three methods to reduce costs 1. Using industry recognised industry recognized internal design standards for data center components, so they consume less power in doing their job. This helps in reducing overall cost. 2. Follow the industry standards for matching the sizing of data center components more closely to the actual IT load so that the components operate at a higher efficiency. This eventually would lead to cost savings. 3. Adopt industry standards recognize d technologies to reduce the need for electric power to supply data center support functions. This would also help in reducing the overall costs. All the three methods are using data center industry standards as a mean of reducing overall costs. Cost savings
หน้า 9
9 4. Data Center Standards current situation in Thailand Standards adoption is at nascent stage in Thailand data center market and adoption is quite low compared to other south Asian economies. There are very few government data centers that have complied with international standards concerning quality of servic e. In Thailand, EGA and PTT public company are the only players that have data center certified from uptime institute. Economies like Indonesia have large number of uptime certified data centers and in comparison Thailand number is quite small. With respec t to TIA, not a single data center has got the certification from the respective governing body. The situation is expected to change in coming years, as the expectations of data center customers are expected to increase in coming years and demand for high ly available data center would be a necessity. Data Center standards challenges in Thailand According to the Natural Resources Defence Council (NRDC), in US data centers in total used 91 billion kilowatt - hours (kWh) of electrical energy in 2013, and they will use 139 billion kWh by 2020. Data centers consume up to 3 percent of all global electricity production while producing 200 millio n metric tons of carbon dioxide. The data centers are producing huge impact on environment and lot of environmental groups are putting pressure on data center operators to use green data center practises to reduce environmental impact of the data centers. By adopting the data center industry best practises, the companies are able to reduce the impact on the environmental . Below are some of the steps that can be taken to reduce the impact on environment. 1. Use of renewable energy: This is one of the most im portant steps towards reducing the environmental impac t of data centers . By using renewable energy companies are able to reduce their carbon foot print , which would lower the impact on the environment. 2. Us e of efficient data centers: Another best way to reduce data centres’ impact on the environment is to make them more efficient by implementing best practices in their design and operations. Environ mental Impact One of the biggest challenges faced by the data center operators is that the standards are expensive to adopt. The standards offer guidelines for operating and maintainin g the data center efficiently. Uptime institute has developed tier system for data center availability and has defined the down time for each of tiers. Tier 1 is bare min imum and tier 4 is the best wit h respect to Uptime. T o reach tier 4 certification data center operators need to have 2N+2 data center redundancy , which means data center need to have double power and mechanical components and also add two more to that. Power and cooling standards prescr ibe to install best in class power and cooling equipment, which increases the efficiency of th e data center. To make data center physically safe, data center operators need to install high end cameras, wedge barriers, layered access control etc. Installing and maintain all these equipment increases the cost exponentially for data center operators. The adoption of standards is quite high in emerging economies, as these economies has low purchasing power capacity and most of the data center operators in the r egion are quite hesitant about heavy capital expenditure. Standards are expensive to adopt
หน้า 10
10 Over the years, the number of standards for data centers have increased at very fast pace globally. It is challenging for data cent er operators to choose between which standards to use and which not to use. Data center standard has been developed for different components of the data center and has also been developed for the specific out put of data centers. Uptime and TIA have been de veloped for availability, ASHARE and NABERS have been developed for power and cooling, PTDCI and HIPPA for data center security related standards, LEED and BISCI for data center design standards, ISO for operational standards, SSAE and ISAE for auditing th e data center standards. C hoosing the rights standards is very important for data center operators due to the below mentioned reasons: a. Every data center has unique needs and it is not essential for the data center to adopt best in class standards. The d ata center operator might not be hosting the very critical information and can follow some essential standards and left out some non - essential standards. b. Data center operator might be hosting banking data and there are specific data center security cer tifications that need to obtain before hosting any banking data. The security certification provides the guidelines that need to be followed to make the data center more secure. Long List of data center standards to choose from As the list of standards is quite long, there is lack of people with skills that have complete understanding of data center standards . There is a long list of standards that are available for data center operators to adopt, but th ere are few people available that have the skill set to understand all the standards available . There are people available that have knowledge of p articular standard, but do not have the knowledge about other standards. This is a huge challenge, as data center operators do n o t adopt multiple stan dards and not knowing which one they should adopt is a big disadvantage . This kind of situation is more prevalent in emerging economies, as there is huge shortage of skilled people in the general workforce. Lack of people with complete understanding of standards This challenge is quite specific to the data center operators in government sector. Most of th e government agencies have fixed budges and these budgets are not much flexible to cover the standards expenses. Many agencies have the intent to adopt the data center standards, but due to budget woes, they are not able to move forward. This relevance of this challenge is expected to go down as the government is going to modernize the agency data centers and more emphasis would be put on the efficiency and environmental effects of data centers. Budget is big issue for standards adoption
หน้า 11
11 Once the data center standards are adopted, another challenge that comes into place is maintaining the standards. There is l ack of people who have full understanding of standards and how to maintain the data center st andards. Adoption of standards is one thing, but confronting to standards is all together new challenge. As the company or any government agency does not adopt any single standard, it is challenging to find people that have understanding of how to adhere t o all the standards that has been adopted. Even if the company or agency finds such people with the required skill set, they are extremely expensive to hire and retain. Lack of people who have full understanding of various standards and their implications Data center operators are not mature enough to understand value behind the adoption of data center standards. Most of the data center operators in Thailand are still in their early stages of the development and adopting industry best practises is not their priority for them . One more thing that is hindering the development of standards is that data center operators are not able to clearly see the ROI behind the investment, an issues which is related to the how mature the market is. This trend can be seen in government as well in private sector. Government sector has shown some maturity in terms of understanding of data centers standards, but due lot of bureaucratic hurdles things don’t move further than that. Data center operators are not experienced enough This challenge is again quite specific to the government and its agen cies. In most of the government offices, the approval process for purchasing any service or product is time consuming. In case of standards, there are large numbers of steps that need to be followed to completely adopt the standards, and it is challenging and time consuming to make budget committee members understand the value and importance of standards. Another issue th at has creates a hurdle for the stand ard adoption is that everything has to be approved at ministry level. If there is no policy at the ministry level, which says that standards should be adopted, it would be quite difficult for the individual agen cy to co nvince ministry to approve budgets for standards adoption . The best scenario in this case would be if the ministry mandates the adoption of standards in every agency under its jurisdiction. Lack of understanding at a bureaucratic level on the i mportance of adopting standards Bureaucracy is hindering the adoption of standards
หน้า 12
12 5. Data Center Standards by Functional Areas Energy and Power Design and Structure Server, Storage and utilization Location and Site Service level Agrement Most the data center operators in Thailand are running their data center on legacy infrastructure and legacy buildings. This issue can be seen more prevalent in government agencies than in enterprise sector, as most of the government data centers are situa ted in large g overnment buildings. To adhere to data center standards, the agency has to remove old IT infrastructure and put in the new infrastructure, which would be very capital intensive for government agency . The legacy buildings structure is a chal lenge, as these building don’t have any space for new equipment which is required if they follow any standards. A data center standard also dictates that data center should be located in place where it can be easily accessible, but it is a challenge for go vernment agencies as it would be highly capital intensive to mov e the data center to new location. Many data center operators are still using legacy infrastructure
หน้า 13
13 1 . Energy and Power Energy is one of the most important components in data centers. Data Centers consume an immense amount of power to perform functions reliably and effectively. The electrical costs in Data Centers typically accounts for 40 - 60% of the total operating costs. Improving energy efficiency of a Data Center is extremely beneficial - it reduces the costs of operation and at the same time, lowers the environmental impact of the facility. Meters : Meters provide data that offers insight into the operation of the data center infrastructure (i.e. power and cooling systems) within a data center. Specific types of meters exist for various reasons, from tracking the use of electricity to analysing the po wer quality in a facility and reporting problems such as transients and harmonics. Within a data center, meters would be in place that measure power (kW), energy (kWh), voltage & amperage, harmonics, power factor, flow rates, temperature & humidity, and mo re. PUE : PUE is the ratio of energy coming into the data center, compared to how much power is actually consumed by IT equipment like servers. This measurement is expressed by a ratio, making 1.0 an ideal, yet almost impossible standard to achiev e. The power usage effectiveness (PUE) rating has become the de facto standard measurement of efficiency in the data center industry. Lighting : Lighting is important part of the data center that has often been ignored by the data center operators. An industry standard recommends using LED fixtures in data centers for three reasons: they consume less electricity, they generate less heat and they ar e nearly 100% dimmable. Sensor based lighting is also used in data center to reduce the energy costs. Redundancy : By redundancy we mean the duplication of critical components or functions of a system with the intention of increasing reliability of the system, usually in the case of a backup or fail - safe. In data centers , the need for redundancy focuses on how much extra or spare power the data center can offer its customers as a back - up during a power outage. Unexpected power outages are the overwhelming usual cause for data center downtime . UPS : Data center operators , when faced w ith the likelihood of downtime, and data processing errors caused by utility power, implement an uninterruptible power supply (UPS) system between the public power distribution s ystem and their mission critical loads. The UPS system design configuration chos en for the application directly impacts the availability of the critical equipmen t it supports.
หน้า 14
14 2 . Design and Structure Cooling : Data center cooling or heat removal is one of the most essential yet leas t understood of all critical IT environment processes. As the latest computing equipme nt becomes smaller and uses the same or even more electricity than the equipment it replaced, more heat is being generated in data centers. Using the latest cooling technologies help the data center operator to reduce the cooling in data center and at the same time increase its efficienc y. The data center infrastructure is central to the IT architecture, from which all content is sourced or passes through. Proper planning of the data center infrastructure design is critical, and performance, resiliency, and scalability need to be carefully c onsidered. Another important aspect of the data center design is flexibility in quickly deploying and supporting new services. Designing a flexible architecture that has the ability to support new applications in a short time frame can result in a signific ant competitive advantage. Cabling : In data center, the various entities make up the system work to together to protect and to manage both current and future equipment’s and the thousands of connections exists between servers and switches and the outlying areas of the network. All of thes e entities are interrelated and connected by the cabling system, which designers and end - users are striving to design for better scalability, flexibility, manageability, availability and lower total cost of ownership is a com op here to help. That is why w e’ve developed this guide as a living document, adding more configurations over time. _____<______________________________________ ____________9___ ____ __________________ ___ ________________________________ _____1____________________2_____ ___=___________ ____ ________2___>_____ - _________ ______>_________________________________________ Physical Security : Data center has various physical threats and p hysical threats to IT equipment include such things as po wer and cooling problems, human error or malice, fire, leaks, and air quality. The data center operators need to protect the data center by installing proper lighting, installing normal CCTV and thermal cameras, wedge barriers at the data center gates and sensors around the data center perimeter. Extra security should be provided to the server room. ___ ________________________________ _____1____________________2_____ ___=_______________ ________2___>_____ - _________ ______>_________________________________ ________ Building Design : The data center buildings are designed in a very specific manner and it is very essential that specific design is being followed to follow industry standards. One of the important features of the building the data center is to design it into zone. The zonal architecture helps in the overall data center security. For building design most of the data centers follow BISCI and TIA. TIA is much more popular among data center players. Many data center players use LEE D industry standard for architectural design of data centers ___ ________________________________ _____1____________________2_____ ___=_______________ ________2___>_____ - _________ ______>_________________________________________
หน้า 15
15 3. Server, Storage and utilization Monitoring : Monitoring plays a very important role in today’s complex data center environment. It helps the data center operators to monitor different components of data center through GUI interface. Initially data center operators were using simple buildi ng management systems for data centers and eventually they installed advanced building management systems. In today’s complex environment the data center operators are using DCIM tools to monitor the data center. ___ ________________________________ _____ 1____________________2_____ ___=_______________ ________2___>_____ - _________ ______>_________________________________________ Fire detection: A comprehensive fire detection and suppression system is required to ensure that life and property are protected. Fire and life safety protection systems (e.g., fire alarms, heat/smoke detectors, carbon monoxide detection, automated fire suppression, extinguishers, and emergency exit routes) should be professionally designed, installed and main tained. In a security zone or high security zone with a raised floor, heat and smoke detection devices must be installed both above and below the floor surface . ___ ________________________________ _____1____________________2_____ ___=_______________ ____ ____2___>_____ - _________ ______>_________________________________________ The data centers are equipped to host / co - locate systems (e.g. Web Servers, Application Servers, Database Servers, SAN, and NAS etc.) to host applications at the data center to use the centralized computing power. Data centers have high availability, centralized authenticating system to authenticate the users to access their respective systems depending on the authentication matrix. The entire infrastructure in th e data center would require monitoring tools and security tools for efficient operation. Utilization and Virtualization: The utilization rate i s defined as the overall extent to which data cente r different components are being used and is usually recorded as a percentage total input. The utilization rates can be calculated for server, network and storage. Understanding the utilization rates help the data center operators to understand the capacit y utilization and plan for the future in case the utilization is quite high. Virtualization means the breaking the physical server in small servers and increased virtualization indicates better efficiency. ___ ________________________________ _____1______ ______________2_____ ___=_______________ ________2___>_____ - _________ ______>_________________________________________ Monitoring: Monitoring tools effectively manage the computing environment of the , including various applications running in t here. A typical data center would include network & security elements, servers, databases, applications etc. Many management software tools would help the data centers to establish and sustain an optimized, on - demand infrastructure, by continuo usly assessing and self - managing the systems, applications and databases. Applications. ___ ________________________________ _____1____________________2_____ ___=_______________ ________2___>_____ - _________ ______>_________________________________________
หน้า 16
16 4 . Location and Site Determining the location of a data center is one of the crucial decisions for a company as it is based on strategy and goals of a company or government. Site selection plays an important role for the same as it will have direct impact on cost and TCO. Ther e are many factors which affect site selection. All these factors should be looked from strategic perspective as nowadays an industry changes its focus and business direction in 5 to 7 years. Location and Site: Data center should be easily accessible from multiple highways and should also have the option to expand in case of increased demand . Data center should location is readily acc essible to authorized employees and f ire and also emergency services are able t o respond qu ickly to incidents. Easy access to electrical power is available from diverse sources and f uture expansion is possible if increased capacity is required for the data centers. ___ ________________________________ _____1____________________2_____ ___=_______________ ________2___>_____ - _________ ______>_________________________________________ Helpdesk: Helpdesk for data center p rovide seamless integration to log incident automatically via system and network management. It also a llows detailed multiple levels/ tiers of categorization on the type of incident being logged. Helpdesk can p rovide classification to differentiate the criticality of the incident via the priority levels, severity levels and impact levels. Helpdesk m ust be able to log and escalate user interactions and requests. ___ ________________________________ _____1____________________2_____ ___=_______________ ________2___>_____ - _________ ______>_________________________________________ Security: Data center security is very important for data center vendors and most of the vendor use advanced level of security measure to protect their IT infrastructure. Most of the vendors use enterprise level firewall, antivirus and vulnerability scans to protect their data centers. Transmission of data securely is also important for data center operators. Data center use advanced encryption technologies to transfer thei r data from one data center to another. ___ ________________________________ _____1____________________2_____ ___=_______________ ________2___>_____ - _________ ______>_________________________________________ Backup: Data center backup is extremely important, as it helps to recover the critical data in case of any major incident. The backup solution should be available for all the available operating systems and should also be capable SAN and NAS based backups. The backup solution would have a GUI platform to ensure smooth administration. The proposed backup solution should be able to write from multiple data streams. ___ ________________________________ _____1____________________2_____ ___=_______________ ________2___>_____ - ____ _____ ______>_________________________________________
หน้า 17
17 5 . Service level Agreement End - to - end service availability of the data center and its independent monitoring is the prime requirement to have reliable, seamless, smooth delivery of the services to the citizens. It is, therefore, necessary that appropriate Service Level Agreements (SLAs) be worked out between government and the Implementing Agency and that an independent Agen cy would be appointed to monitor the performance with reference to the SLA and related aspects Disaster recovery: Disaster recovery focuses on the information or technology systems that support business functions. It is a subset of business continuity, which involves planning to keep all aspec ts of a business functioning in the midst of disruptive events. From a digital government perspective, controls and protections can be broadly grouped under the term Disaster Recovery (DR) . Data center o perators can have a single DR site or multiple DR sites. ___ ________________________________ _____1____________________2_____ ___=_______________ ________2___>_____ - _________ ______>_________________________________________ Tier: Tier 1 to 4 data center is nothing but a standardized methodology used to define uptime of data center. Tier 4 data center considered as most robust and less prone to failures. Tier 4 is designed to host mission critical servers and computer systems, with fully redundant subsystems (cooling, power, network links, storage etc.) and compartmentalized security zones controlled by biometric access controls methods. Naturally, the simplest is a Tier 1 data center used by small business or shops. ___ ____________ ____________________ _____1____________________2_____ ___=_______________ ________2___>_____ - _________ ______>_________________________________________
หน้า 18
18 6. Refined Maturity Model for Data centers Data Center Level explanations We have developed the five maturity levels for standards for government agencies. W e have already identified the current level of readiness for standards among different government agencies. The below table defines the minimum level of standard that each of the four type of data centers should follow. If an agency feels that due to sensi tive of data that it handles, it should be at higher level then should definitely move to upper levels. Level 1 Definition : Data center that are following level one standard, would be the data centers that can provide very basic form of service. Processes are usually ad hoc and the organization usually does not provide a stable environment. In spite of this ad hoc and chaotic environment, maturity lev el 1 organizations are able to provide services effectively. 2 Level 2 Definition : Data center that are following level two standards would realize that data center infrastructure and operations are critica l to the business. The data center would start taking actions with respect to equipment, processes and people to further gain operational control and visibility. 3 Level 3 Definition : At level three maturity data centers wold be g aining efficiencies and service quality through standardization, policy development, governance, and implementing proactive/cross - departmen tal processes. This could help the data center become more standardized and work towards becoming more efficient. 4 Level 4 Definition : At level four maturity data centers wold be managing data center like any other business. The data center operator would adopt standards that would help to make the data center more customers focused in the long run. More sophisticated technologies become part of the data center , as data center tries to achieve higher efficiencies. 5 Level 5 Definition : At level five maturity data centers would be adopting standards that would help data centers to become nimble, adaptable and innovative . The organization’s ability to rapidly respond to changes and opportunities is enhanced through adoption of best in class standards. 1
หน้า 19
19 Parameter Sub Parameter’s Level 1 Level 2 Level 3 Level 4 Level 5 Energy consumption No Meters installed Building level metres installed Switch board metering installed Circuit Level metering installed End User level metering installed Power usage effectiveness PUE not measured Started measuring PUE. Total annualized kWh consumption. Measured at output Ideal PUE 2 - 2.5 Started measuring PUE. Total annualized kWh consumption. Measured at output 1 .6 - 1.99 PUE measured, Total annualized kWh consumption. Measured at output Ideal PUE 1.4 - 1.59 PUE measured, Total annualized kWh consumption. Measured at output Ideal PUE <1.39 Energy & Power Redundancy Our components are not redundant (N) We have one redundancy component (N+1) We have redundancy component plus two more components ( N+2) We have double redundancy components( 2N) We have double redundancy components(2N+1) Lighting We are using only fluorescent lights Optimize lighting - Use of more efficient fluorescent lights Use LED lights in all parts of DC Using intelligent lighting system in data center Daylighting and/or light pipes/tubes used to augment and reduce dependency on electrical lighting systems UPS We do not use UPS for power interruptions and rely only on generator UPS System efficiency - not measured We use a standby/of fine UPS for power interruptions UPS System efficiency measured - 50% - 60% We use a line interactive UPS System efficiency - measured - 61% - 80% We use a double conversion UPS System efficiency - 81 % - 90% Efficient UPS - Use of double conversion eco mode UPS System efficiency - >90% Cooling We use air cooled self - contained system and do not measure cooling output We using chilled water system for cooling and Cooling System Efficiency - >1.5 kw/ton We are using DX systems in data centers and do not measure cooling metrics Cooling System Efficiency - 1 kw/ton 1.49 kw/ton We use direct fresh air evaporative coo ling system and start tracking cooling metrics Cooling System Efficiency - .99kw/ton .5 kw/ton We use indirect free air evaporative cooling system and keep an target for cooling metrics Cooling System Efficiency - <.5 kw/ton Colour Coding & Naming We do not use any color coding or naming in DC We use color coding and naming in server room only We use color coding and naming convention using TIA standard guidelines in all parts of data center We use color coding and naming convention for the whole DC using TIA standard guideline in all data centers in an area We use color coding and naming convention using TIA standards in multiple data center sites in different parts of the country Design & Structure Security Assessment Basic security with simple CCTV Biometric access, CCTV on infra, lighting on perimeter Sensor for perimeter, high resolution cameras Wedge barrier, access control attached with CCTV in grey spaces Thermal cameras in server room, Threat assessment conducted
หน้า 20
20 Building design Building don’t have zones, building designed not per any standards Data center has been divided into different zones Data center has been designed using basic level standards of TIA or BISCI or both Data center would follow complete guide lines of TIA or BISCI or both. Data center has been designed as per LEED standard Monitoring No automated or centralized monitoring system for mechanical, electrical, and facility systems. Use of Building Management system. Use IP - enabled meters that supply data to a building management system Automated and centralized monitoring system inclusive of key critical mechanical, electrical, and facility systems Automated and centralized monitoring system inclusive of key critical mechanical, electrical, facility, and key IT systems Automated and centralized monitoring system inclusive of key critical mechanical, electrical, facility and key IT systems. Analytical and real - time data manage ment capability such as integrated dashboards, and DCIM solutions. Utilization & Virtualization Utilization not measured Tracking average monthly and peak utilization across the data center Storage 40% - 60% utilization Network utilization greater than 40% in the data center Virtualized 10% - 30% Average monthly CPU utilization is greater than 20% in the data center Storage 61% - 70% utilization Network utilization greater than 60% in the data center Virtualized 31% - 50% Average monthly CPU utilization is greater than 35% in the data center Storage 71% - 90% utilization Network utilization greater than 70% in the data center Virtualized 51% - 80% Average monthly CPU utilization is greater than 50% in the data center Storage 91% + utilization Network utilization greater than 80% in the data center Virtualized >81% Monitoring IT infrastructure and software We do not monitor IT infrastructure in our data center We plan to use server and database monitoring tools We plan to use web server monitoring tools in data center Monitoring tool to be integrated with enterprise management system Reporting from monitor ing tools would enhance service efficiency Server, Storage and Utilization Help desk We do not have any helpdesk We use helpdesk for data center that requires minimal support 8 hours operations 5 days a week We use helpdesk that requires 24 hours support 5 days a week with L1 support facility We use helpdesk that requires 24hr support; 7 days a week with L1 and L2 support We use helpdesk that requires 24 hr. support, 7 days a week with L1, L2, L3 support Backup No backup solution available Back up their data and send these backups to an off - site storage facility Weekly backup their data and send it to offsite storage facility Daily backup their data and send it to offsite storage facility Mission critical data is electronically vaulted
หน้า 21
21 Security for IT infrastructur e and data We do not use any network security and encryption technologies We use basic firewalls that have high latency and low traffic handling capacity. We also use simple encryption technologies We use enterprise firewall with high performance and concurrent connection capability. We use simple encryption technologies We use enterprise firewall with high performance and concurrent connections capability. Encryption technologies are SLL or better We use next generation firewalls that can secure discrete application layer transactions and includes intrusion prevention and application layer gateway. Use advanced Encryption technologies. Location & Site Accessible and expansion Data center is not easily accessible and expansion not possible Move data center to a more accessible location in the same area Data center to be located at new location where it can be accessed from multiple roadways Data center is expandable in single phase Data center can be expanded in multiple phases Power and network availability Data center has only 1 source for power and network. Data center has single sources for power and two sources for network. Data center two sources for power and 2 sources for network Data center must use alternative energy sources for power in data centers and 2 sources for network Data center must set a target for the usage renewable energy for power and 2 sources for network SLA Disaster recovery Data center does not have any disaster recovery plan Data center has start using shared DR site for recovery Has developed a DR plan and are using multiple shared DR sites. Has developed the DR plan and implemented the DR plan with single Disaster recovery site. Has devel oped the DR plan and implemented the DR plan with multiple disaster recovery sites. Tier and Response time Data center does not have any measure downtime/uptime. Data center is tiered and have a downtime of >29 hrs./year but less than 50 hrs./yr. Data center is tiered and has a downtime of 15 - 29 hrs./year Data center is tired and has a downtime of 2 to 15 hrs. Data center is tired and has a downtime of <2 hours/year
หน้า 22
22 7. Benefit Realization – Standards Improved Energy Measurement Capabilities Adopting standards would help the data center in improving energy measurement capabilities. As the data center would install modern meters in their data centers, they would be able to measure the energy consumed accurately. This would enable data centers to measure energy consumed over a period of tim e and identify components t hat consume most of the energy. Achieving high levels of PUE PUE is industry defined metric to measure the usage of all the power equipment’s in the data center. To achieve higher PUE level s data center would have to concentrate on using its equipment’s efficiently. As the data center would achieve higher PUE, efficiency levels would also increase and that would ultimately lead to cost savings. Better Redundancy Redundancy plays an important role in case of any failure of any mechanical equipment. Moving to higher levels would make the data centers resistant to any equipment failure, as it would have spare for e ach of the equipment’s. This would help data center to continue providing services, in case of any large equipment failure. Optimized lighting Data centers are usually using fluorescent lights, which are not efficient at all and consume lot of energy. LED lights co nsume less energy and can run for much longer time, compared to fluorescent lights. Intelligent lighting system would help the data center to reduce energy costs, as lights would be used only when needed. This would help the data centers to reduce energy c osts. Efficient UPS Data centers are using UPS systems which are okay for some data centers, but as the usability of data centers would increase, need for more efficient data center is required. Efficient UPS would help in reducing the time to move to UPS power, in case of an y failure. This plays an important role, when we are using data centers that are require to have high availability all the time.
หน้า 23
23 Better Cooling Systems Cooling is an important component of data center and it consumes large amount of energy. Data center need to use cooling systems that are appropriate for it to work properly. Improved cooling systems would not be completely dependent on power to provide co oling, but would use outside air to provide cooling to data center. This would help in reducing the costs and improving the efficiency of data center. Colour Coding and naming Colour coding and naming would not help data center in saving any costs directly, but would provide the ability to resolve issues quickly. Using colour coding and naming would help the data centers to locate any problem in any data center quickly. This would help in improving the efficiency of data centers. Improved Physical Security and better design Data Centers keeps lot of sensitive information and having good physical security is important. This would also help the data centers to detect any physical threat before it can cause any damage. Better design would help the dat a center to improve its security by dividing its data center into different zones. Physical and IT Infrastructure monitoring Monitoring systems for the building would help in monitoring all the mechanical and IT equipment. This would help understanding the usage and health of equipment in the data center. Modern tools would help in asset identification and future capacity estimation. IT monitoring tool would help in the keeping a check on servers , data bases and web servers. This would also help in detecting any issue early on, thus resulting in preventing large failure Better Utiliz ation and Virtualization levels Measuring Utilizing for IT components are important as it helps the data center operates to know how efficiently server, storage and network are being used. More utilization would provide good ROI for the capex spend. Improved virtualization levels would provide ideas of how many severs are being virtualized, as low virtualization would mean low efficiency. Helpdesk with better advanced capabilities Most of the data centers do not have capability to handle technical problems related to data centers operations. Establishing Help desk with advanced capabilities would help data center to resolve many issues quickly and also help in saving costs, as most of the trouble shooting would be done internally.
หน้า 24
24 Improved backup capabilities Backup is one of the important elements for any agency. Instead of taking backups on ad - hoc basis, if taking regularly would help in retrieving information in case of any technical issue. Weekly and daily backups are essential, as there is lot of sensitive information being kept in centralized data centers. Security of IT infrastructure This is one of the most important standards for data centers in the region. Data security breaches are quite widespread and the costs related to that are humongous. Having best in class of security for IT infrastructure would help the data centers avoid any unwanted intrusions, which would help them save lot of costs in the long run. More accessible and expandable Accessibility is important for a data center, as in case of any disaster it would be important for emergency services to reach there on time to save the infrastructure that is present in data center. As the demand for data centers would increase, it would be necessary for data center operators to plan for expansion initially, as this would help in reducing overall future costs. Multiple sources of power Having multiple sources of power and network would help the data centers in switching to alternative sources in case of a ny emergency. This would help in reducing the downtime and thus saving lot of costs for data centers. Disaster recovery sites Having disaster recovery site and well defined plan is important for data center operators. In case of any event which is leads to closing all the services in the data center, disaster recovery sites would help in running the data center services for its c ustomers. This disaster recovery plays an important role in business continuity for data centers. Tier and response time Tier corresponds to the downtime that any particular type of data center is having. Lesser the downtime and response time, more would be availability of service for its customers, which would lead more satisfied customers.
หน้า 25
25 8. Current State of Agency data center in Thailand The focus group discussion was conducted in the March 2017 and people from government agencies attended the event. Questionnaires were designed to get answers for questions related to strategy and standards. The standards questions were divided into five levels and in below mentioned bar charts and average of responses has been taken for analysis purpose. 2.5 1.7 2.1 2.0 2.9 2.4 0.0 0.5 1.0 1.5 2.0 2.5 3.0 3.5 Meters PUE Redundancy Lighting UPS Cooling Energy and Power Average Level Meters PUE Redundancy Lighting UPS Cooling 2.9 2.8 2.4 3.4 3.3 Utilization Monitoring IT infrastructure Helpdesk Backup Security 0.0 2.0 4.0 Server storage and utilization average level Utilization Monitoring IT infrastructure Helpdesk Backup Security 2.7 2.1 2.5 2.5 Cabling Physical Security Building Design Monitoring 0.0 1.0 2.0 3.0 Design and Structure Average level Cabling Physical Security Building Design Monitoring
หน้า 26
26 3.1 2.6 Disaster Reovery Tier 0.0 1.0 2.0 3.0 4.0 SLA Average level Disaster Reovery Tier 2.5 2.2 Accessible and Expandable Dual Supply 1.8 2.0 2.2 2.4 2.6 Location and site average level Accessible and Expandable Dual Supply
หน้า 27
27 9. Frost & Sullivan Analysis of Future State for Standards for Data Centers The above diag ram gives us an overview of the levels for the four data center models from our analysis. We have five primary areas for the standards namely energy and power, design and structure, server storage and utilization, location and site and finally SLA’s . We h ad developed nineteen parameters form five main parameter from our analysis. Th e nineteen parameters are considered to be most important and the same nineteen sub parameters were also use in the focus group discussion. The levels for some of the sub parame ters for four models would be same as what we have got in focus group discussion and for some the levels would be different. We will discuss the five main areas of standards, their sub parameters and what are the reasons behind our analysis for keeping the m on different or same level s when compared to results that we got from the FGD. (Levels ) Five Four Three Two One Standards Our Analysis Agency DC Level Our Analysis Ministry DC Level Our Analysis Cross DC Level Our Analysis G services Level Energy consumption Power usage effectiveness Redundancy Lighting UPS Cooling Color Coding Security Assessment Building design Monitoring Utilization & Virtualization Monitoring IT infrastructure and software Help desk Backup Security for IT infrastructure and data Accessible and expansion Power and network availability Disaster recovery Tier and Response time Frost & Sullivan Future Recommended Level
หน้า 28
28 10. S ervice L evel Agreements - Colocation Service Description This Service Level Agreement (“SLA”) defines the performance parameters and quality level of the Colocation Services provided by Vendor to the Agency (Government) under the Agreement. This document clarifies both Parties’ responsibilities and procedures to ensure the Agency needs are met in a timely manner. This SLA and the Agreement shall be interpreted and applied together as a single instrument. In the event of any inconsistency between the SLA and the Agreement, the provisions of the Agreement shall prevail. Service level Agreement Definition All electrical circuits would order with one (1) primary and one (1) redundant circuit for failover per cabinet. Aggregate draw may not exceed the thresholds defined herein. If Agency’s actual power requirem ent exceeds the listed threshold, Agency may consider procurement of additional contiguous space to accommodate power consumption and heat dissipation. Power The network equipment would connect co - located servers to the outside network, providing seamless bandwidth and Internet connectivity. Network connectivity is provided from A and B sources to every server for redundancy. Top of rack switches will be connected via A and B sides. The redundant network connection allows properly config ured servers to retain network connectivity during most regularly scheduled maintenance and unplanned events. Maintenance will be performed on only one side of the network at a time when possible. Network Conditioned Space Computer Room Air Conditioning (“CRAC”) units are strategically placed in each Data Center to ensure that the appropriate ambient temperature and humidity thresholds are met. Cooling Data Centers are equipped with both water - based and non - water - based fire suppression systems, depending on location and local fire codes. In addition to these fire suppression systems, hand - held fire extinguishers are also placed strategically throughout the Data Center. Fire suppression systems are tested annually to ensure functionality. Fire Detection
หน้า 29
29 Service Reporting Service availability, usage and capacity reports, if applicable, are generated on a monthly basis using various Monitoring and Management tools. Service availability, usage and capacity reports are available to Agency upon request. Service Reporting Facility Access and Physical Security includes controlled access and egress doors; controlled access permissions and access request methods; and managed key, access card and/or biometric systems for access control. CCTV/IP Video is used to monitor access, egress and infrastructure. Data center vendor reserves the right to access (or to allow third parties to access) any part of the Data Center or facility at a ny time for safety and security reasons, including Agency cage space or Agency cabinets. Physical Security Agencies can opt for lockable cabinet rack space. Cabinets are four - post racks with combination lockable doors and side panels. Agency authorized contacts will have a unique PIN to access their rack space. Full Rack – dedicated 42U rack Half Rack - dedicated 21U rack Third of a Rack – dedicated 14U rack" Racks For Agency’s that require floor space without a rack (i.e., full rack SAN, etc.), Data center vendor offers leased floor space options based on the total square feet required. Floor Space Caged space is an option available to Agency’s who are managing the Agency equipment installed at a Data Center in whole o r in part. Caged space is comprised of a mesh wall around Agency’s racks/cabinets with dedicated connectivity infrastructure. This connectivity is built on an Agency - by - Agency basis and no pre - wired cabling is provided Caged Space Remote Hands is provided to Agency’s for an additional charge, and it involves the most basic activities of an on - site technician performing as the "eyes, ears, and fingers" on the Agency’s behalf. Remote Hands
หน้า 30
30 Service Level Metrics Availability SLA Cumulative Service Unavailability Agency Credit < 60 min 0 >60 min and < 2hours 1 >2 Hours and <3 hours 2 >3 Hours and <4 hours 3 15 hours 15 Service Availability goal for power in the data centers is 99.99%. This equates to 4.32 minutes of downtime monthly based on a 30 - day month. Data Center vendor guarantees to keep at least one channel of power in service in order to reach our Service Availability g oal for power. Agencies should use both channels of power that are available in the data center for their equipment if possible Power SLA Data center vendor to provide average temperatures of 65 - 78 degrees Fahrenheit over a 24 hour period within the cold aisles of the data center. Temperature fluctuations may temporarily occur in the 64 - 80 degree Fahrenheit range. Data center vendor reserves the right to modify the upper and lower limits in accordance with ASHRAE recommendations for data ce nter operations of equipment. Cooling SLA Data center vendor should provide a 99.999% network uptime guarantee providing uninterrupted transit to the internet. Interrupted transit is defined as 100% packet loss to the internet and data center v endor guarantees Zero packet loss internal to DC’s network. Network SLA
หน้า 31
31 Response Time Response Time Solution The loss of one or more critical components of a system resulting in a major impact on the Agency’s business. The problem would have a high visibility to the Agency and their business operations, with no work around possible. 15 minutes 80% in 4 hours The loss of one or more critical components of a system resulting in serious degradation of services to Agency’s business. Priority 2 incidents are usually characterized by: 1 hour 80% in 1 WD · The Agency cannot work as normal but a bypass is available · The Agency is not yet experiencing serious disruptions, however, there is a potential to do so if the request is not solved. Minor impact on service delivery. A non - critical part of an application, Operating system or server is affected by the problem. The problem has a moderate visibility to the Agency and a low impact on their business operations. Normal fault calls fall into this category. 4 hours 80% in 4 WD This is the default priority level assigned to faults. Note: All calls logged by fax or email automatically become Priority 3 or lower. Fault has little or no operational impact. Included in this area are requests for information. 1 NWD 80% in 11 WD
หน้า 32
32 Maintenance Data center vendor will notify Agency’s about both scheduled and unscheduled maintenance. Services may not be available during the maintenance periods. Overall Maintenance Data Center infrastructure work can require extended outages for all services in the data center. Examples of such work include changes to our electrical, mechanical, network or firewall infrastructure. Infrastructure maintenance Scheduled Maintenance will mean any maintenance where (a) Agency is notified 72 hours in advance, and (b) that is performed during a standard maintenance window of 10 PM to 6 AM local time. Information regarding Scheduled Maintenance will be provided to Agency's designated point of contact. Data center vendor reserves the right to perform mai ntenance outside of Scheduled Maintenance during an emergency situation. Scheduled maintenance Unscheduled maintenance tasks that require service downtime will be announced as soon as possible to the Agency Unscheduled maintenance Data Center will maintain a mailing list of Agency contacts who will be notified of planned maintenance and unplanned events. Agencies must notify data center vendor of any changes to contact information as part of providing escalation path information. Contact lists will be reviewed periodically. Change notification Maintenance of the data center chilled water and environmental systems. Monitoring and control of climate conditions in all the data centers is required. Responding to climate - related alerts resulting from variations from climate conditions that exceed system thresholds (for example, excessive temperatures, hot spots, etc.). Climate Control Early warning detection system Individually zoned, double - interlocked, pre - action fire suppression system. Dry pipe with water suppression in the event of a fire Maintenance of all sensors and alarms Maintenance of the fire suppression system Monitoring of, and respon se to, all related alerts and alarms Compliance with relevant certification and fire code requirements Fire Detection and Suppression Maintenance of the uninterruptible power supply system. Maintenance of the back - up generators and related systems Connection to the electrical source Power
หน้า 33
33 Agency Responsibilities Agency agrees to designate Primary and Secondary Agency Support Representatives (CSR). The Primary CSR will serve as the primary liaison with OPS for the delivery and conduct of support services. The Secondary CSR will be fully authorized to assume this r ole in the absence of the Primary CSR. The CSR facilitates the delivery of support services with OPS by establishing priorities, refining requirements, coordinating scheduling, handling procurements, and disseminating information among appropriate staff. C SR may appoint technical contacts and will provide and maintain as current a list of personnel authorized to access their designated rack space. Agency Support Agents Agency will check in with the Operator on duty for access to the secure area where servers are located. Agencies will be issued a specific combination for access to their rack space. OPS will retain a master key that allows access to all rack spaces in order to execute emergency or planned maintenance work that has been coordinated with Agency. An emergency in this case is defined as any unforeseen circumstance that requires immediate action regardless of the impact to services provide on the Agency’s servers. The emergency shall be determined to exist by OPS. Access Agency is responsible for the purchase, license and maintenance costs of all hardware, software, and network components directly associated with their specified SLA. Agency will work through OPS to obtain and install all network cables, KVM connectors and cables. Agency is required to consult with OPS on all hardware and network related procurements to be housed in the Co - location area prior to placing orders to ensure the products and/or services best meet Agency needs and are certified for standard 19” ra cks and related power, HVAC, etc. requirements. Ordering All software provided by the Agency for use on the Agency’s computers/servers shall be properly licensed in sufficient quantities to cover actual usage. Licensing Compliance Agency agrees to use rack space only for server and related hardware. Agency agrees to consult with OPS prior to placing additional hardware in their rack space and understands that such additions may impact on one or several elements of the ir SLA. Agency agrees to coordinate with OPS prior to any equipment relocation within the rack space that involves KVM or network connectivity. Rack Utilization Agency is responsible for the administration and security of their systems and explicitly agrees to adhere to existing security and use policies and procedures. Consistent with policy and practices, Data center vendor reserves the right to disconnect any server from the network that poses a threat or which may be directly tied to th e assessment of a perceived threat to the environment because of security exposures or any condition that puts the surrounding area to threat, including potential violations of existing laws or policies. Security System Agency is responsible for the administration of their servers. As an option, Data Center vendor offers this service under a different service level agreement. While operating system version and patch level is left to the discretion of the Agency, data ce nter vendor reserves the right to disconnect any server from the network that poses a threat to the environment because of back levelled software or patches. Systems Management
หน้า 34
34 Terms Agency is responsible for backups and restores to their servers. As an option, data center vendor can offers this service under a different service level agreement (contact OPS for details). Restore and Backup In general, the Agency is responsible for moving, shipping, storing, and delivery of its property. Operation will work with the Agency to facilitate changes, movement and addition of servers and network - related equipment. Equipment Relocation/ Storage Agency is responsible for development and implementation of their own business continuance plan. OPS will provide information on the ITS Business Continuance Plan upon request, but replacement of equipment and business continuity remains the responsibility of the Agency. If Agency wants to have a hot spare in the rack, it will be treated as just another piece of equipment at no additional charge. However, if it needs KVM or network ports, the Agency will be assessed an additional charge for that service. Business Continuance This Service Agreement is in effect beginning XYZ data at 8:00 a.m. through XYZ data at 5:00 p.m., unless renewed or terminated as described below. Effective Term All Service Agreements are due and payable no later than XYZ date. If a signed agre ement has not been received by that date, defined services will be discontinued until a signed agreement is received Billing One party may terminate this Service Agreement upon the failure of the other party to substantially perform the duties specified in this Agreement. This Service Agreement is terminated 30 days after written notification of this failure, unless the failing party corrects the failure to the satisfaction of the terminating party. On termination, the Agenc y is only liable for payment for services performed in accordance with the provisions of this Service Agreement prior to the effective date of the termination. Agency will coordinate with OPS for the removal of their equipment. Vendor will process appropr iate refunds upon termination. Termination Changes to this Service Agreement can take place when both parties agree in writing. Amendments The Agency will be given an opportunity to extend the term of this Service Agreement at least 60 days prior to the expiration date. In the event that either party wishes to re - negotiate any terms or conditions of this Service Agreement, they shall notify the other party of the proposed changes and, if required, a meeting will be held to discuss and a gree upon revisions to the Service Agreement. Renewal
หน้า 35
35 11. Service L evel Agreements - Third party Cloud Definitions Agreement The Cloud Computing services agreement between agency and Vendor, inclusive of all schedules, exhibits, attachments and other documents incorporated by reference P1 (Priority 1) The service is unavailable for all users; or an issue prevents payroll or tax processing and/or financials quarter - end or year - end close processing. P2 (Priority 2) The service contains a bug that prevents Agency from executing one or more critical business processes with a significant impact and no workaround exists. P3 (Priority 3) The service contains a bug that prevents Agency from executing one or more important business processes. A workaround exists but is not optimal P4 (Priority 4) The service contains an issue that may disrupt business processes where a workaround is available or functionality is not imperative to Agency's business operations. Confidential Information This means any information that a disclosing party treats in a confidential manner and that is marked “Confidential Information” prior to disclosure to the other party. Data This means all information, whether in oral or written (including electronic) form, created by or in any way originating with agency and end users, and all information that is the output of any computer processing, or other electronic manipulation, of any information that was created by or in any way originating with agency and End Users, in the course of using and configuring the Services provided under this agreement, and includes agency Data, End User Data, and Protected Information. Downtime This means any period of time of any duration that the Services are not made available by vendor to agency for any reason, including scheduled maintenance or Enhancements.
หน้า 36
36 Service Details End User Data Includes end user account credentials and information, and all records sent, received, or created by or for end users, including email content, headers, and attachments, and any Protected Information of any end User or third Party contained therein or in any logs or other records of Vendor reflecting End User’s use of Vendor Services. Services This means vendor’s computing solutions, provided over the Internet to agency pursuant to this agreement, that provide the functionality and/or produce the results described in the Documentation, including without limitation all Enhancements thereto and all interfaces. Third Party This mean s persons, corporations and entities other than vendor, agency or any of their employees, contractors or agents. Agency data This includes credentials issued to agency by vendor and all records relating to agency’s use of Vendor Services and administration of End User accounts, including any protected Information of agency personnel that does not otherwise constitute Protected Information of an End User. End User This means the individuals (including, but not limited to employees, authorized agents, Third Party consultants, auditors and other independent contractors performing services for agency; any governmental, accrediting or regulatory bodies lawfully requesting or requiring access to any Services; Agencies of agency provided services; and any external users collaborating with agency) aut horized by agency to access and use the Services provided by Vendor under this Agreement. IaaS The capability provided to the consumer is to provision processing, storage, networks, and other fundamental computing resources where the consumer is able to deploy and run arbitrary software, which can include operating systems and applications. The consumer does not manage or control the underlyin g cloud infrastructure but has control over operating systems, storage, and deployed applications; and possibly limited control of select networking components PaaS The capability provided to the consumer is to deploy onto th e cloud infrastructure consumer - created or acquired applications created using programming languages, libraries, services, and tools supported by the provider. The consumer does not manage or control the underlying cloud infrastructure including network, servers, operating syst ems, or storage, but has control over the deployed applications and possibly configuration settings for the application - hosting environment.
หน้า 37
37 Cloud Deployment Model Service Levels SaaS The capability provided to the consumer is to use the provider’s applications running on a cloud infrastructure. The consumer does not manage or control the underlying cloud infrastructure including network, servers, operating systems, storage, or even individual application capabilities, with the possible exception of limited user specific applicatio n configuration settings. Private Cloud The cloud infrastructure is provisioned for exclusive use by a single organization comprising multiple consumers (e.g., business units). It would be owned, managed, and operated by the government organization and it exists on premises. Public Cloud The cloud infrastructure is provisioned for open use by the general public. It may be owned, managed, and operated by a business, academic, or government organization, or some combin ation of them. It exists on the premises of the cloud provider. Hybrid Cloud The cloud infrastructure is a composition of two or more distinct cloud infrastructures (private, community, or public) that remain unique entities, but are bound together by standardized or proprietary technology that enables data and application portability (e.g., cloud bursting for load balancing between clouds) Community Cloud The cloud infrastructure is provisioned for exclusive use by a specific community of c onsumers from organizations that have shared concerns (e.g. mission, security requirements, policy, and compliance considerations). It may be owned, managed, and operated by one or more of the organizations in the community, a third - party, or some combinat ion of them, and it may exist on or off premises. Vendor represents and warrants that the Services will be performed in a professional manner consistent with industry standards reasonably applicable to such services. Vendor represents and warrants that the Services will be operational at least 99.99% of the time in any given month during the term of this Agreement, meaning that the outage or Downtime percentage will be not more than .01%.
หน้า 38
38 Data Privacy Vendor shall provide agency with monthly reports documenting its compliance with the service levels detailed herein. Reports shall include, but not be limited to, providing the following information: a) Monthly Services availability by percent time, dates and minutes that Se rvices were not available, and identification of months in which agreed upon service levels were not achieved; b) Average transaction processing time per week, the fastest and slowest individual transaction processing time per week, the percent of transactions processed that meet the service levels stated herein, and identification of weeks in wh ich agreed upon service levels are not met. If the S ervices availability falls below 99.99% in any month, vendor shall provide agency with a credit of that month’s bill for Services according to the table below. Availability Percentage of Credit 99.60% to 99.69% 10% 99.50% to 99.59% 20% 99.00% to 99. 49% 30% 97.00% to 99.00% 50% Below 97.00% 75% Service Availability Cloud Ser ver availability 99.99% Cloud Network availability 99.99% Cloud Storage availability 99.99% Vendor will use agency Data and End User Data only for the purpose of fulfilling its duties under this Agreement and for agency and its End User’s sole benefit, and will not share such data with or disclose it to any Third Party without the prior written consent of agency or as otherwise required by law. By way of illustration and not of limitation, Vendor will not use such data for Vendor’s own benefit and, in particular, will not engage in “data mining” of Agency or End User Data or communications, whether through automated or human means, except as specifically and expressly required by law or authorized in writing by agency Vendor will provide access to agency and End User Data onl y to those Vendor employees, contractors and subcontractors (“Vendor Staff”) who need to access the data to fulfil Vendor’s obligations under this Agreement. Vendor will ensure that, prior to being granted access to the data, Vendor Staff who perform work under this Agreement have all undergone and passed criminal background screenings; have successfully completed annual instruction of a nature sufficient to enable them to effectively comply with all Data protection provisions of this Agreement; and possess all qualifications appropriate to the nature of the employees’ duties and the sensitivity of the Data they will be handling.
หน้า 39
39 Data Security and integrity All facilities that store and process agency data will implement and maintain administrative, physical, technical, and p rocedural safeguards and best practices at a level sufficient to secure such data from unauthorized access, destruction, modification, or disclosure. Such measures will be no less protective than those used to secure vendor’s own data of a similar type, an d in no event less than reasonable in view of the type and nature of the data involved. Vendor shall maintain the administrative, physical, technical, and procedural infrastructure associated with the provision of the Services to agency in a manner that is, at all times during the term of this Agreement, at a level equal to or more stringent than anywhere else Without limiting the foregoing, vendor warrants that all agency data will be encrypted in transmission (i ncluding via web interface) and in storage at a level equivalent to or stronger than 128 - bit level encryption. Vendor shall at all times use industry - standard and up - to - date security tools, technologies and procedures including, but not limited to ant i - virus and anti - malware protections and intrusion detection and reporting methods Vendor will configure the Services to filter spam while permitting communications from Third Party Internet Protocol addresses identified by agency as legitimate. Physical and Environmental Security - Controls that provide reasonable assurance that access to physical servers at the production data center is limited to properly authorized individuals and that environmental controls are established to detect, prevent a nd control destruction due to environmental extremes. Monitoring the network and production systems, including error logs on servers, disks and security events fur any potential problems. Such monitoring includes: a) Reviewing changes affecting syste ms handling authentication, authorization, and auditing; b) Reviewing privileged access to Workday production systems; and c) Engaging third parties to perform network vulnerability assessments and penetration testing on a regular basis.
หน้า 40
40 Data Compromise Response Data retention and disposal Vendor shall report, either orally or in writing, to agency any data compromise involving agency or end user data, or circumstances that could have resulted in unauthorized access to or disclosure or use of agency or end user da ta, not authorized by this agreement or in writing by agency, including any reasonable belief that an unauthorized individual has accessed agency or end user data. Vendor shall make the report to agency immediately upon discovery of the unauthorized disclo sure, but in no event more than 48 hours after vendor reasonably believes there has been such unauthorized use or disclosure. Oral reports by vendor regarding data compromises will be reduced to writing and supplied to agency as soon as reasonably practi cable, but in no event more than 48 hours after oral report. Immediately upon becoming aware of any such Data Compromise, vendor shall fully investigate the circumstances, extent and causes of the data compromise, and report the results to agency and continue to keep agency informed on a daily basis of the progress of its investigation until the issue has been effectively resolved. Vendor’s report discussed herein shall identify: (i) the nature of the unauthorized use or disclosure, (ii) the agency or End User Data used or disclosed, (iii) who made the unauthorized use or received the unauthorized disclosure (if known), (iv) what vendor has done or shall do to mitigate any deleterious effect of the unauthorized use or disclosure, and (v) what corrective action vendor has taken or shall take to prevent future similar unauthorized use or disclosure. Vendor will retain data in an end User’s account, including attachments, until the end user deletes them or for t he time period mutually agreed to by the parties Using appropriate and reliable storage media, Vendor will regularly backup agency and end user data and retain such backup copies for a minimum of 12 months. Vendor will retain logs associated with end user activity for a minimum of 12 months.
หน้า 41
41 Data transfer upon termination or expiration Data Location Interruptions in service; suspension and termination of service; changes to se rvice Upon termination or expiration of this agreement, vendor will ensure that all agency and end user data are securely transferred to agency, or a third Party designated by agency, within 30 days. Vendor will ensure that such migration uses facilities and methods that are compatible with the relevant systems of agency, and that agency will have access to agency and end user data during the transition. In the event that it is not possible to t ransfer the aforementioned data to agency in a format that does not require proprietary software to access the data, Vendor shall provide agency with an unlimited use, perpetual license Vendor will provide agency with no less than 90 calendar days ’ notice of impending cessation of its business or that of any Vendor subcontractor and any contingency plans in the event of notice of such cessation. This includes immediate transfer of any previously escrowed assets and data and providing agency access to vendor’s facilities to remove and destroy agency - owned assets and data. Vendor will provide a full inventory and configuration of servers, routers, other hardware, and software involved in service delivery along with supporting documentation, indicating which if any of these are owned by or dedicated to agency. Vendor shall implement its contingency and/or exit plans and take all necessary actions to provide for an effective and efficient transition of service with minimal disruption to agency. Vendor will work closely with its successor to ensure a successful tr ansition to the new service and/or equipment, with minimal downtime and effect on agency, all such work to be coordinated and performed no less than 90 calendar days in advance of the formal, final transition date Vendor guarantees that the location of the data would be in Thailand only and in no case would vendor move the data to other countries. If the cloud vendor plans to move the data from one location to another within Thailand, vendor needs to obtain permission from the agency for such movement. Vendor should also provide X days of notice to agency for the movement. Vendor shall be responsible for providing disaster recovery Services if vendor experiences or suffers a disaster. Vendor shall take all necessary steps to ensure that Agency shall not be denied access to the Services for more than five 10 hours in the event there is a disaster impacting any vendor infrastructure necessary to provide the Services. Vendor shall maintain the capability to resume provisions of the Services from an alternative location and via an alternative telecommunications route in the event of a disaster that renders the Vendor’s primary infrastructure unusable or unavailable
หน้า 42
42 Vendor warrants that the minimum technical requirements for access to and operation of the Services If future enhancements to the Services require use of newer versions of these web browsers, vendor will provide a minimum of X days written notice to agency prior to implementing such enhancements. From time to time it may be necessary or desirable for either the agency or vendor to propose changes in the Services provided. Such changes shall be made pursuant to the Change Control Procedu re. Automatic enhancements to any software used by vendor to provide the Services that simply improve the speed, efficiency, reliability, or availability of existing Services and do not alter or add functionality, are not considered “changes to the Service s” and such enhancements will be implemented by vendor on a schedule no less favourable than provided by vendor to any other Agency receiving comparable levels of Services. Vendor will provide agency with X calendar day’s prior notice of any times t hat the Services will be unavailable due to non - emergency maintenance or enhancements. In the event of unscheduled and unforeseen times that the Services will for any reason, except as otherwise prohibited by law, Vendor will immediately notify agency and cooperate with agency’s reasonable requests for information regarding the services being unavailable (including causes, effect on Services, and estimated duration). Vendor may suspend access to services by an end user immediately in response to an a ct or omission that reasonably appears to jeopardize the security or integrity of vendor’s Services or the network(s) or facilities used to provide the Services. Suspension will be to the minimum extent, and of the minimum duration, required to prevent or end the security issue. The suspension will be lifted immediately once the breach is cured.
หน้า 43
43 Technical support Correction of Services errors Priority Description Target Response Time Target Update Time Target Fix Time P1 Production software unusable/Production cloud servers inaccessible 1 hour, Providers executive notified of issue 1hr Immediate - work commences and continues until issue resolved or workaround deployed P2 Partial software functionality unusable/Partial service unavailable 4 hours 1 Day 2 days, subject to available maintenance slot P3 Cosmetic issue 1 working day 1 working day Next software release/service update P4 Information request 2 working days 2 working day n/a During the term of this agreement vendor will provide agency with ongoing technical support for the Services at no less than the levels and in the manner(s) specified. Vendor may not withdraw technical support for any Service withou t X months advance written notice to agency, and then only if vendor would be allowed to withdraw the technical support. Agency shall receive at its option the general help desk technical support offered by vendor to its other customers. Irrespective of vendor’s general technical support offerings, vendor shall provide agency option with the following technical support Vendor shall provide technical support to agency for the purpose of answering questions relating to the Services, including (a) c larification of functions and features of the Services; (b) clarification of the documentation; (c) guidance in the operation of the Services; and (d) error verification, analysis, and correction, including the failure to produce results in accordance with the documentation Such assistance shall be provided by vendor twenty - four (24) hours a day, seven (7) days a week via a toll - free telephone number and live, online chat staffed by help desk technicians sufficiently trained and experienced to ide ntify and resolve most support issues and who shall respond to all agency requests for support within fifteen (15) minutes after receiving a request for assistance.
หน้า 44
44 Training Transition Assistance Vendor shall provide agency with training for the purposes of understanding and using the Services (“Training Services”). Training Services will be provided by vendor as detailed below at no additional cost to agency. Training Services will be provided by vendor at agency at mutually agreeable dates and times, but no later than one hundred eighty (180) calendar days following the Effective Date of this Agreement Vendor will develop, provide and implement the transition assistance to support Agency’s successful and uninterrupted transition from its current solution, or other solution in this area, to vendor’s services. Transition Assistance will be provided by vendor detailed below at no additional cost to agency. Transi tion assistance will be provided by vendor at agency location at mutually agreeable dates and times, but no later than ten X calendar days following the Effective Date of this Agreement. Within no more than ten X calendar days after the effective dat e of this agreement, vendor shall, at its own expense, provide qualified individuals to (a) uninstall existing solution, (b) implement the Services, and (c) assist in testing of the Services to ensure that they are functioning in accordance with the terms of this Agreement.
หน้า 45
45 Fees, invoicing, payment and pricing Agency agrees to pay all net undi sputed amounts due to vendor in accordance with the Services fee schedule set forth below. Such fees will be payable after access to the Services is provided to agency and within thirty X calendar days of agency’s receipt of Vendor’s invoice or the invoice due date, whichever is later. Agency shall not be subject to late payment fees. Agency need to specify services fee details here including a description of the service being acquired, list price and agency cost per unit of each service being acquired, quantity of units initially being acquired, the term for each service being acquired, and any other pertinent considerations or limitations applicable to the services being acquired. Agency will have the option to acquire additional Services throughout the duration of the Agreement Agency will have the option to acquire additional Services for a monthly prorated portion of per unit cost in order that all Services acquired maintain the same term. Services acquired during the initial purchase shall be provided by vendor to agency for an initial one (1) year term (the “Initial Services Term”) commencing on the “Services Commencement Date” (as hereafter defined). The Initial Services Term shall be renewable f or successive one (1) year terms (“Extension Terms”, and collectively with the Initial Services Term, the “Services Term”) upon written notice from agency to vendor. For the purposes of this agreement, the term “Services Commencement “shall refer to the fi rst day of the month following the month in which the Services were initially provided to agency. After the first anniversary of the Initial Services Term, the Services shall be renewable for successive one (1) year terms (“Extension Terms”) upon written notice from agency to Vendor. Vendor should include pricing changes notice X days before the change (requirement to give notice prior to pricing changes) Vendor should mention number of pricing changes time frame limitation (limitation on how many pricing changes can occur within set time frame) Demand Pricing (requirement to match lower pricing offered to other similar entities when quantities, services, etc., are comparable) Costs for Special Services/Additional Quantities/Etc. (costs related to items not specifically included in the original contract scope)
หน้า 46
46 Terms and Termination Warranties, representations and covenants Agency may terminate this agreement upon X calendar days written notice. Vendor shall provide written notification regarding upcoming annual Agreement term expiration dates no less than X calendar days prior to expiration dates. Agency may terminate this Agreement immediately upon Vendor's any substantive breach of the terms of t his Agreement. Agencies shall have the right to discontinue use of the Services for any reason, and shall receive a full refund of all payments, for a period of X calendar days after the Services Commencement Date (the “Warranty Period”). Services Warranty: Vendor represents and warrants that the Services provided to agency under this agreement shall conform to, be performed, function, and produce results substantially in accordance with the Documentation. Vendor shall offer agency warranty coverage equal to or greater than that offered by vendor to any of its customers. Disabling Code Warranty: Vendor represents, warrants and agrees that the services do not contain and agency will not receive from vendor any virus, worm, trap door, b ack door, timer, clock, counter or other limiting routine, instruction or design, or other malicious, illicit or similar unrequested code, including surveillance software or routines which may, or is designed to, permit access by any person, or on its own, to erase, or otherwise harm or modify any agency system or Data (a "Disabling Code"). Intellectual Property Warranty: Vendor represents, warrants and agrees that vendor has all Intellectual Property Rights necessary to provide the services to agenc y in accordance with the terms of this agreement; vendor is the sole owner or is a valid licensee of all software, text, pictures, audio, video, logos and copy that provides the foundation for provision of the Services, and has secured all necessary licens es, consents, and authorizations with respect to the use of these underlying elements; the Services do not and shall not infringe upon any patent, copyright, trademark or other proprietary right or violate any trade secret or other contractual right of any Third Party; and there is currently no actual or threatened suit against vendor by any Third Party based on an alleged violation of such right. This warranty shall survive the expiration or termination of this Agreement. Date/Time Change Warranty. Vendor represents and warrants to agency that the Services provided will accurately process date and time - based calculations under circumstances of change including, but not limited to: century changes and daylight saving time changes. Vendor must repair any date/time change defects at vendor’s own expense.
หน้า 47
47 Audit Compliance with Laws Warranty: Vendor represents and warrants to agency that it will comply with all applicable laws, including its tax responsibilities, pertaining to the Agreement and its provision of the Services to agency. Vendor is responsible for keeping accurate records related to its performance and obligations under this Agreement. In particular, records will be kept documenting any price, cost or budget computations requ ired under the Agreement. Vendor agrees that agency or its authorized representative has the right to audit any directly pertinent books, documents, papers and records related to transactions and/or performance of the terms and conditions of the Agre ement. Vendor shall make available to agency or its representative all such records and documents for audit on vendor’s premises during regular business hours within X business days of a written request for availability. Vendor agrees to either: (a) allow agency to make and retain copies of those documents useful for documenting the audit activity and results; or (b) sequester the original or copies of those documents which agency identifies for later access by agency. The right to audit shall include periodic examinations of records throughout the term of the Agreement and for a period of X years after its termination.